Tuesday, November 17, 2026

More Improvements

In the sunroom, the rough in wiring and installation has been complete, but the final insulation has to be added under Rudy's bedroom.  Temporary light fixtures have been installed before insulation and drywall is to be added, hopefully this winter.








I found these nifty battery back up, LED emergency path lights at Rona, marked down from $45 to $20... so I picked up five of them... Two are installed in the basement, with one each to be installed on the main floor, the second floor, and the attic.

This one is located on a former junction box, which looks a whole lot better now with a device mounted, rather than a blank steel cover plate. The location was perfect at the bottom of the steps to the basement.






Hard wired, interconnected smoke and CO alarms have been finally installed, two in the basement, three on the main floor, two upstairs, and one each in the attic, and yes, even the belvedere.








The last two outlets on the second floor to be wired are in Rudi's room, and are accessed from underneath via the sunroom...  Yes, I had one end of the wire dangling from the ceiling in the little used sunroom, but here are the ends now, carefully coiled up where no one can grab them... I mean, they are also not energized, so there is that, lol











 

Monday, November 16, 2026

A Covid Induced Hiatus, and more...

This summer, after close to eight years of working far too much during the pandemic, and also working far too much following the pandemic, I somehow found my motivation to get back to improving the Field House, after the better part of a decade of benign neglect.


I don't know why this box was left empty.  There are three test outlets for each of the main portion of the panel and the backup or emergency portion of the panel.  A GFCI, a regular outlet controlled by the GFCE, and an outlet with a built in switch.



And now complete, properly labelled.






Not only was toilet paper in short supply during the pandemic, so were Stab-Lok circuit breakers.  For a time I jumped a couple of low draw circuits into an extension cord... I know, I know.



But earlier this summer, I purchased additional circuit breakers, and finally installed them this fall, finishing the long,  mostly installed circuit panel for the house.







A few years ago, close to the end of the pandemic, Rudi and I re roofed the front sunroom.  Although the roof and the step flashing was long completed, I never installed counter flashing.  Thankfully, Rudy's experience as an apprentice sheet metal worker obviated the need for me to do some rudimentary flashing work myself.  Look at this incredible job on a single piece, multi step counter flashing. 










I can't believe someone did this, but they did. Probably when the house was upgraded to township water, I can't fault the previous owners for this, really.



A new freeze proof faucet spigot, installed right through the brick.






The decrepit old deck entrance on the back of the house.. My plan is to remove it entirely, and build a slightly larger walk out deck, along with a ground level deck at the bottom...



Well look at what someone hid under the shitty deck they built thirty years ago! a ton of rubble, and a cast concrete patio and set of stairs.. interesting.






Well look what I found under the sink in the kitchen! A misaligned, poorly installed, caulked drain, with unnecessary bends in the trap.



Well this is better, a new center drain, and better aligned trap... Admittedly, still an S trap, but vastly superior to the original set up.




Tuesday, March 7, 2017

Main Bathroom Renovation - Part Infinity, But at long last, Pictures of the finished product!









Thursday, October 27, 2016

Main Bathroom Renovation - Part Sixteen - Shluter Kerdi Walk In Shower


The plumbing rough in, with hot and cold Pex supply lines at bottom feeding soldered copper elbows into the main control valve(black),  The mixed temperature water leads up to the diverter (silver), which splits it to the right - Pex runs to handheld shower rough in, and the left - Pex runs to main rainshower head rough in directly above. Everything is carefully blocked out for support and spacing from the proposed finish wall.



A slose up of the main rainshower head and handheld shower head rough in on the left, and main supply control  valve on the right. It helps to keep everything centered! The Kerdi base in the kit is 32 inches wide, and the tape measure is run from cement board to cement board.



The Shluter Kerdi membrane installed, showing the tiled floor and main control valve on the left, and all openings for shower on the right (Main control valve, diverter, handheld and rainshower heads)



Showing the test fitting the stainless drain piece and the shower floor tile (left). and installed after tiles are set, but before grouting (right). The Kerdi drain piece fits ever so neatly in the space taken up by four tiles. This is also where the tiling starts, at and around the drain, then to the head wall of the shower, then down the length of the shower and out to the sides.



The subway tiles climbing the shower wall being laid over the Kerdi Membrane, plus the door opening tiles installed and taped to keep them in place.



A view of the virtually finished walk in shower.  All Moen shower hardware installed, the door frame, tiles are installed and caulked, the outer door trim is in place and primed, and the frameless tempered glass door also installed. The walk in shower has two pot lights, located on center line, about 14 inches from each end, controlled by a dimmer switch.  I all looks a little better than half bad, in my humble opinion.. And it does not leak... and it actually drains properly!

Tuesday, October 21, 2014

Main Bathroom Renovation - Part Fifteen


The wall below the bathroom showing the vertical pex runs for the shower and the main bath vanity, along with assorted fished electrical.




After laying the last of the ceramic tile, I had enough mortar to bed the Shluter Kerdi shower base into the show stall. The full 32 x 60 was used, it just had to be sanded about 1/32 inch from each side to lay in properly.



Yay more issues. It appears whoever painted the first coat over the old paint (not us) on the trim inside the old closet door either didn't prep properly, or used unsuitable primer over the old oil based paint. With little effort, the overlying layers peeled off with ease.

Main Bathroom Renovation - Part Fourteen


Laying down the ceramic tile. The Shluter Ditra-Heat requires the tile be laid using non-modified thinset mortar. I had some minor issues with the first mortar batch being a little thin, and using a trowel with notches that were a little big, in hindsight. A fair amount of mortar came up in the numerous tile gaps and had to be cleaned away.



Looking into the corner between the main bath vanity (rough in visible  on the left) and the walk in shower door (just visible as well on the right).



Diagonally opposite, the corner where the rough in plumbing for the clawfoot tub is located. The door opening is the pocket door to the water closet.

Main Bathroom Renovation - Part Thirteen


The right hand end of the kitchen bulkhead showing (from the right) 3" toilet drain, 3" vertical vent stack (the one that passes up the newly built wall), 2" drain from clawfoot tub, and then a 90 degree bend to continue vertically downward to the basement.



From the left end of the kitchen bulkhead one can barely make out the 2" drain from the shower, then the horizontal drain, to which the 1.5" drain from the main bath vanity joins about halfway, then just to the right of the photo this drain joins the three inch waste stack.



The 2" drain from the left joining the 3" drain from the right. The pex supply lines are those that run through the floor serving the clawfoot tub, toilet, and vanity in the water closet.



It's difficult to imagine that the waste plumbing visible in this bulkhead was previously installed through the floor joists of the bathroom. Acccck!



I spent a total of one hour and thirty five minutes in this position, generally in increments of between two and six minutes each! Not fun, whatsoever...

Main Bathroom Renovation - Part Twelve - Schluter Ditra Heat Floor Installation


Ditra flooring with Ditra Heat cable installed, main bath vanity will be located in the open space on the right, and the clawfoot tub in the open space on the left. The Ditra membrane was installed using latex modified thinset, over a 1/2 inch ply sub laid on top of  3/4" ply sub. The lower ply was glued and screwed into all joists using 2" flooring screws, and the top layer of ply was screwed in lines across the joists, using 1-1/4" flooring screws.



A closer look at the Ditra with heating cable. The kit included 5 sheets of Ditra underlayment, and I had to purchase three extra to ensure I had enough.



The heated to unheated cable interface, which must be located in the Ditra floor. To ensure the top was flush with the top of the Ditra, a small cavity had to be removed with a chisel.



Installation of one of the two temperature sensors. As with the heat to non heat cable interface, the ditra had to be cut back, and a small amount of ply scraped away using an OLFA knife.



The two temperature sensors in place. Two as one is a primary, and the second a redundancy back up, in case the primary fails.